I Old Project
Location: Fangchenggang City, Guangxi Province
Company: Guangxi Shenglong Metallurgy Co., Ltd
Equipment: 2*1770m3 blast furnaces
Iron-making production capacity: 3.0595 million tons per year (34,500
tons of which was left over from last replacement)
Location: Chengde City, Hebei Province
Company: Chengde Shengfeng Steel
Equipment: 2*650m3 blast furnaces
Iron-making production capacity: 1.4834 million tons per year
II New Project
Company: Guangxi Shenglong Metallurgy Co., Ltd
Construction site: Fangchenggang City, Guangxi Province
Equipment: 2*2725m3 blast furnaces
Iron-making production capacity: 4.54 million tons per year
Start time: July 2020
Production time: December 2022
Note: the capacity that can be replaced in this plan totaled 454.29
million tons, of which 2,900 tons of ironmaking capacity was reduced. |