Rio de Janeiro, July 2nd, 2021 - Vale S.A (“Vale”) informs that is
commissioning its loading activities at ship loader 6 (“CN6”) at the
Ponta da Madeira Maritime Terminal (“PDM”), in São Luís, Maranhão, after
a 5 months maintenance, as previously announced.
The maintenance of CN6, which evolved the substitution of over 60% of
its components, did not impact PDM’s monthly iron ore shipment
schedule.
On January 14th, 2021, a fire occurred at CN6 at the Southern berth of
Pier IV ("P4S"). The fire was controlled, without casualties or
environmental damage. During the maintenance period, the P4S sustained
its shipping activities using its second ship loader (CN7), which was
not affected by the fire.
Source: Vale |
|